Open Projects

Community Grants

Year Township Project Name Project total $ Awarded Status of Project
2019 AMHERST ENGLE DITCH RESTORATION PH. 2 $111,035.00 $64,410.00 Contract awarded to Mark Haynes Construction - 90% complete
2020 AMHERST ENGLE DITCH RESTORATION PHASE 3 $154,500.00 $129,000.00 Under design
           
2019 BROWNHELM GORE ORPHANGE HILLSIDE EROSION $54,000.00 $5,400.00 Design
2020 BROWNHELM HILLSIDE EROSION GORE-ORPHANGE RD. $60,900.00 $49,500.00 Under design
           
2019 COLUMBIA FOLLEY ROAD $15,000.00 $7,500.00 Complete
2020 COLUMBIA COLUMBIA HAWKE RD. ROADSIDE DRAIN $14,976.60 $5,597.00 Under Construction
           
2020 HUNTINGTON NEW LONDON-EASTERN RD CULVERT #401 $134,375.00 $60,000.00 Contract awarded to Catts Construction
           
2020 LAGRANGE KOBELT DITCH PHASE 4  $91,000.00 $91,000.00 Out to Bid on October 1, 2020
           
2019 GRAFTON CROCKER ROAD $50,000.00 $50,000.00 Contract awarded to Cornerstone Construction - under construction
           
2018 PITTSFIELD BROWN LATERAL $57,800.00 $57,800.00 Petition in Process
2019 PITTSFIELD Quarry Road Lateral $130,000.00 $10,000.00 Design
2020 PITTSFIELD QUARRY ROAD LATERAL #1 $144,250.00 $134,250.00 Under Design
           
2019 SHEFFIELD DUNTON ROAD $29,800.00 $26,820.00 Design

 

Mini Grants

Year Township Project Name Project total $ Awarded Status of Project
2019 SHEFFIELD Mayfield Street Storm Infrastructure $2,345.00 $1,750.00 Plans approved by County
2020 AMHERST Hidden Valley Catch Basin Replacements $9,200 $5,000 Complete
2020 COLUMBIA Crossover Pipe Replacement for Aldridge Ave & Colfax Ave $5,035 $1,963 Complete
2020 GRAFTON Chamberlain Road Erosion Repair Project $10,213.16 $5,000 Complete
2020 CARLISLE Calann Drive Catch Basin & Squires Street Catch Basin $1,560 $1,248  

 

Planning Grants

Year Township Project Name Project total $ Awarded Status of Project
2019 ELYRIA Storm Sewer Improvemnt Rambler to Griswold at CSX $4,800.00 $3,840.00  
2020 EATON Flooding in Vicinity of 9543 Island Road $4,000.00 $3,200.00  
2020 LAGRANGE Foster Ditch Planning Grant

$10,000.00

$4,000.00  
2020 HENRIETTA Baird Road Project

$5,000.00

$4,000.00  
2020 WELLINGTON Watercourse West of Hawley Rd & North of Cemetery Rd

$4,000.00

$3,800.00  

District Projects

Name Costs Project Status
Kelner Ditch   Plan Review
Plas/ Grafton Rd $40,000 plus 2019 Community Grant Contract awarded to Denes Concrete, Inc.

Completed Projects

Community Grants

Mini Grants

District Projects